Does anyone have any knowledge of solar panel farms ? we have 9 or 10 acres and have given a thought too having panels. The fields are grazed by sheep at the moment so that could continue after the instalation. I used to think that you could catch a cold at the end of the panels life but i see they do have a secondhand value and not a negative value.

Any thoughts ?
 

Kannon Fodda

LIFE MEMBER
Feb 26, 2019
2,704
8,365
Seek and Ye May Find
Funster No
58,768
MH
Autotrail V-line 540
Exp
I Make Schoolboy Errors!
Two main issues.

Planning consent

Connection to the grid. This can be a big issue and many projects for wind and solar are on long term hold waiting for national grid infrastructure.
 
Sep 17, 2017
5,752
10,791
Birmingham, UK
Funster No
50,575
MH
A-Class
Exp
2017
You'd probably be well above the power generation to count as domestic. So you'd probably have to negotiate a commercial contract to get paid for your kWh that you squirt into the grid.
 
Dec 2, 2019
3,689
7,965
Amersham
Funster No
67,145
MH
van conversion
Exp
Since 2019
Planing not so much, but grid connection maybe not even up to scratch to support additional generation. Unless grid upgrades are done.
The DNO will say yes, as long as you pay for the upgrade to take your generation.
 
Sep 17, 2017
5,752
10,791
Birmingham, UK
Funster No
50,575
MH
A-Class
Exp
2017
This suggests 10 acres is the economic lower limit... Although that might have shifted.

Subscribers  do not see these advertisements

 
Jul 29, 2022
705
1,110
Watford, Hertfordshire, UK
Funster No
90,232
MH
Swift Kon-Tiki 599 S
Exp
Since 2021
Not read then, but Googling "how to install a solar farm" returns these:

1. Everything You Need to Know About Solar Farm Requirements

2. The Complete Guide to Solar Farms
 
Oct 6, 2021
574
938
Funster No
84,698
MH
PVC
They are going to build one in the field next to us. They have just started moving equipment onto the field. However, expect a very, very long job before its up and running. We were first notified about the intention to build one 6-7 years ago. Planning applications not only for the solar farm, but the underground cable to connect it to the nearest point of the National Grid, which is only a couple of miles away. Incidentally there were no objections to the planning applications.
 
Oct 8, 2014
1,660
3,102
Wiltshire
Funster No
33,737
MH
Autotrail Excel 600B
Exp
Previous VW Camper + Caravan
A developer wants to build this 2000 acre one on farmland near us. :(

Screenshot 2024-05-25 162755.png
 
OP
OP
Roger S
Oct 31, 2017
561
1,232
Kent
Funster No
51,209
MH
Carthago T149
Exp
Since 2016
Thank you for your replies, I will give it some more thought.

It so usefull asking a wide range of people with varied experiences and views, rather than just searching google as you dont know from what biast an artical is written.

Subscribers  do not see these advertisements

 
Oct 9, 2019
5,030
17,659
Todmorden
Funster No
65,104
MH
Van conversion
Exp
FUNSTER in a PVC
Maybe talk to Octopus to see what their requirements are in respect of size, kit etc, and obviously what will they pay you for the power generated.
 

Join us or log in to post a reply.

To join in you must be a member of MotorhomeFun

Join MotorhomeFun

Join us, it quick and easy!

Log in

Already a member? Log in here.

Latest journal entries

Funsters who are viewing this thread

Back
Top